A quick guide to claims arising under a construction contract

A quick guide to the typical claims that may arise on a construction and engineering project

These include claims a contractor may make (such as loss and expense, extensions of time and for variations) and claims an employer may make (such as for defective work and liquidated damages). They apply to the jurisdictions of England and Wales.

Why do claims arise under a construction contract?

Construction projects rarely run entirely smoothly: additional works may be requested by the employer or become necessary when things are “discovered” on site; delays may mean the building takes longer to complete; or it may cost more than the parties originally contracted for.

These are common claims:


What the contractor may claim from the employer

A contractor may make a claim against the employer for more time and money (loss and expense) and for the cost of changes to the works (as variations or as a quantum meruit).

A claim for an extension of time to the completion date

A claim for loss and expense

Common heads of loss and expense claimed include:
prolongation costs;
finance charges;
loss of profits;
general disruption; and
wasted management time.

A claim for the cost of variations

A claim for payment under a quantum meruit

not agreed a contract or not agreed all the terms, including the price for the work;
an agreement to pay a reasonable sum for the work done; or
agreed a scope of work under the original contract and the work falls outside that scope (and the parties did not have or did not use a variation procedure in the contract).

What the employer may claim from the contractor

The employer may have a claim against the contractor because the works are of a poor quality or are defective, or because the project is delayed.

A claim for poor workmanship and/or defects in the works

A claim for liquidated damages


What the employer may claim against the professional consultant

On construction projects, professional consultants often act as the contract administrator (valuing and certifying the works) as well as undertaking a design role. Generally, on building contracts, the professional consultant administering the contract is an architect; on engineering contracts, it is usually an engineer. Occasionally, the employer may appoint a project manager or quantity surveyor to administer a contract.

Professional consultants should perform their services in accordance with the implied or express duty of care in their professional appointment.

The professional consultant may be liable to the employer for:

An employer claims its losses caused by a breach of contract or the negligence of a professional consultant as general (unliquidated) damages.

What the professional consultant may claim against the employer

What are the differences on engineering projects?

Most engineering projects are procured on different forms of contracts to construction projects (such as FIDIC, NEC3, IChemE and IMechE, but many of the types of claims that could arise are the same.

Some key differences include:

PLC Construction

This quick guide was produced by PLC Construction

Practical Law Company (PLC) is the leading provider of practical know-how for lawyers. We employ a team of more than 170 legal experts, all of whom have had significant experience in practice. They create and maintain the resources that help you work more efficiently.

Related Articles

Have your say

Sign in to make a comment on this story.

Sign In

Text size

Desktop Site | Mobile Site