Changes to public procurement regulations

Traditionally, contractors in the UK have found the decision to challenge a contracting authority they suspect of foul play in a tender process a difficult one. Not wanting to be seen to “bite the hand that feeds them”, has often resulted in contractors accepting a tender rejection they believe to be “a bit fishy”. However, in the depths of the economic downturn - where work is now harder to come by and every contract counts - this is changing. Contractors, in increasing numbers, are challenging tender processes which they believe do not satisfy the requirements of the Public Contract Regulations 2006.

Many of these complaints/challenges are dealt with amicably between the contractor and the public sector body before they reach the courts, but there have been an increasing number where contractors have sought to lodge formal proceedings and seek their remedy through judicial means.

Following a recent change in the Public Contracts Regulations 2006 contractors wishing to pursue remedies through judicial means will have a much shorter time period within which to do so (30 days instead of the previous three months). This change, set out in the Public Procurement (Miscellaneous Amendments) Regulations 2011, is a result of the ECJ ruling in Uniplex where it was held that the previous time limits were incompatible with European law. The court will still have the discretion to extend this time-limit where it deems there is a good reason for doing so, but only up to a maximum of three months from the contractor becoming aware of the breach.

Other amendments introduced include:

Clarity of time-scales has therefore come at a cost and the overall impact of the 30 day time-limit is likely to produce a rash of scantily-detailed claims by contractors seeking to protect their position.

Rebecca Rees is a partner at Trowers & Hamlins LLP

Related Articles

Have your say

Sign in to make a comment on this story.

Sign In

Text size

Desktop Site | Mobile Site